TEMPORARY POWER

TEMPORATY POWER SOLUTIONS.

Evolution Site provides temporary power equipment, load planning, electrical distribution, cabling, installation and technical support for events and temporary projects across the UAE, Saudi Arabia and the wider GCC.


Our inventory includes generators, distribution boards from 32A to 630A, PowerLock and secondary cabling, splitter cables, adapters, cable ramps, transformers, fuel equipment and temporary site lighting.


Clients can hire individual items or appoint Evolution to calculate, install and support a complete temporary power system.

POWER SOLUTIONS

GENERATORS, DISTRIBUTION AND SUPPORT

The correct temporary power solution depends on what requires power, where each load is located, when the equipment will operate and which systems must remain available if part of the supply is interrupted.


Evolution Site can plan and provide the equipment required to generate and distribute power across temporary sites.

LOAD PLANNING + CALCULATIONS


Assessment of all electrical loads, operating periods, and usage patterns to determine the anticipated maximum demand. Appropriate diversity and demand factors will be applied to establish distribution system requirements, including transformers, switchboards, cables, and backup power systems. Suitable contingency and spare capacity will be included to accommodate future load growth and ensure reliable operation.

GENERATORS



Generator capacities and configurations will be determined based on calculated loads, operating schedules, peak demand, and critical power requirements. Fuel storage, refuelling arrangements, equipment positioning, noise considerations, protection systems, and backup capacity will also be considered to maintain a safe, efficient, and uninterrupted temporary power supply throughout operations.

PRIMARY DISTRIBUTION


Planning, selection, and installation of high-capacity electrical distribution systems to transfer power safely and efficiently from the main generation source to key areas across the site. The system will be designed around calculated load requirements, distribution distances, and operational demands, with suitable switchgear, cabling, protection devices, and connection points. Cable routing, equipment positioning, system resilience, and spare capacity will also be considered to provide a reliable and flexible temporary power network.

SECONDARY DISTRIBUTION


Power will be distributed from the primary network to individual operational areas, temporary facilities, and equipment through appropriately positioned distribution boards, cables, and connection points. Cable sizing, circuit protection, load balancing, accessibility, and equipment locations will be carefully coordinated to provide a safe, flexible, and reliable power supply throughout the site.

CABLE MANAGEMENT



Cable routes will be carefully coordinated throughout the site to maintain safe, organised, and unobstructed working areas. Suitable cable ramps, covers, supports, and protective systems will be provided where cables cross pedestrian routes, vehicle access points, and operational zones. Consideration will also be given to segregation, accessibility, installation conditions, and ongoing inspection to reduce trip hazards, prevent damage, and maintain reliable power distribution.

SITE LIGHTING



Temporary lighting will be strategically positioned across compounds, access routes, working zones, and operational areas to provide suitable visibility throughout the site. Lighting levels, fixture locations, coverage, glare control, power supply, and operating hours will be considered to support safe movement, efficient working conditions, and continuous operations during periods of low light or darkness.

INSTALLATION + TECHNICAL SUPPORT


Qualified electrical personnel will be available throughout the project to manage installation, testing, commissioning, and ongoing operation of the temporary power systems. Technical teams will provide system monitoring, routine inspections, fault finding, repairs, adjustments, and maintenance as required, while ensuring compliance with site safety procedures. Support will continue through final shutdown and de-rig to ensure all electrical activities are completed safely and efficiently.

Image description

LOAD PLANNING

CALCULATING THE POWER REQUIREMENT.

Temporary power planning starts with the electrical load rather than the generator.


Evolution Site can assess the equipment and facilities requiring power to establish anticipated demand and develop an appropriate generation and distribution strategy.


Loads may include technical production, event lighting, broadcast facilities, HVAC, catering equipment, refrigeration, temporary offices, hospitality areas, site facilities, vehicle charging and operational lighting.

DESIGNED AROUND THE LOADS AND LOCATIONS.

Total connected load is only one part of the calculation. The position of each load, its operating period and its importance to the overall operation also influence how the system should be configured. Our planning process therefore considers individual and combined electrical loads, starting and operating demand, single-phase and three-phase requirements, simultaneous equipment use, site layout and cable distances, operating hours, distribution-board locations, critical systems, backup and redundancy requirements, and any future or anticipated load changes.


This information allows generation, distribution and cabling to be selected around the project’s actual requirements. If loads or site layout change during planning, the power strategy can be reviewed and updated before installation, ensuring the final system remains efficient, reliable and correctly matched to operational needs.

Image description

POWER GENERATORS

GENERATORS, TRANSFORMERS AND FUEL EQUIPMENT.

Temporary generation may be required where permanent electrical infrastructure is unavailable, insufficient or too far from the areas requiring power.


Evolution Site maintains selected generator, transformer, fuel and battery equipment within its own inventory. Where a project requires additional generation capacity or a different configuration, suitable equipment can be incorporated into the wider temporary power package.

SELECTED FOR THE PROJECT REQUIREMENT.

Generator selection is influenced by the anticipated load, phase requirements, operating hours, fuel capacity, the design of the distribution network, site conditions and the level of contingency required. Each of these factors helps determine both the size and the configuration of the generation plant so that it can support the project reliably throughout its duration.


Depending on the scale and layout of the event, the generation strategy may use a single generator, multiple independent generators serving separate zones, or synchronised units that operate together to supply a larger temporary network. The chosen approach balances efficiency, resilience and operational flexibility.


Generation capacity is always planned alongside distribution and cabling so that power can be delivered safely and efficiently to the equipment using it. This integrated approach ensures that cable runs, distribution boards and generator placement work together as a coherent system rather than as isolated components.

GENERATORS + TRANSFORMERS

Generator - 5kVA - Single Phase
SS-PGN005-T01
Sync Generator - 60kVA - Single Phase
SS-PGN060-T01
3kVA 220V - 110V Transformer 
​SS-PTX3KV-T01

FUEL TANKS

Fuel Tank - Double Bunded - 500 Gallon
SS-PFT500-T01
Fuel Pump
SS-PFTPUM-T01

BATTERIES

Large Batteries 12V
SS-PBT12V-T01
Image description

ELECTRICAL DISTRIBUTION

DISTRIBUTION BOARDS FROM 32A TO 630A.

Evolution Site holds an extensive inventory of temporary electrical distribution boards for primary and secondary distribution.


Boards are available in ratings from 32A to 630A, allowing temporary networks to be configured around different electrical loads, site layouts and operating requirements.


Distribution boards can be hired individually or supplied as part of a complete temporary power system.

FROM THE SOURCE TO THE FINAL LOAD

Temporary electrical distribution may involve several stages. Higher-capacity feeds carry power from the source into the primary network before secondary boards and cables distribute it to individual areas and equipment.


The required arrangement will depend on the available supply, electrical demand, cable distances, board locations and connections required at each destination.


Our inventory includes 32A, 63A, 125A, 400A and 630A distribution boards, together with the primary and secondary cables, tails, splitters, jumpers and adapters required to connect them.

DISTRIBUTION - 32A

32A DB Type 1
SS-PDB032-T01
32A DB Type 2
SS-PDB032-T02
32A DB Type 3
SS-PDB032-T03
32A DB Type 4
SS-PDB032-T04
32A DB Type 5
SS-PDB032-T05
32A DB Type 6
SS-PDB032-T06

DISTRIBUTION - 63A

63A DB Type 1
SS-PDB063-T01
63A DB Type 2
SS-PDB063-T02
63A DB Type 3
SS-PDB063-T03
63A DB Type 4
SS-PDB063-T04
63A DB Type 5
SS-PDB063-T05
63A DB Type 6
SS-PDB063-T06
63A DB Type 7
SS-PDB063-T07
63A DB Type 8
​​SS-PDB063-T08
63A DB Type 9
SS-PDB063-T09

DISTRIBUTION - 125A

125A DB Type 1
SS-PDB125-T01
125A DB Type 2
SS-PDB125-T02
125A DB Type 3
SS-PDB125-T03
125A DB Type 4
SS-PDB125-T04
125A DB Type 5
SS-PDB125-T05
125A DB Type 6
SS-PDB125-T06
125A DB Type 7
SS-PDB125-T07
125A DB Type 8
SS-PDB125-T08
125A DB Type 9
SS-PDB125-T09

125A DB Type 10

SS-PDB125-T10

DISTRIBUTION - 400A + 630A

400A DB Type 1
SS-PDB400-T01
400A DB Type 2
SS-PDB400-T02
400A DB Type 3
SS-PDB400-T03
400A DB Type 4
SS-PDB400-T04
400A DB Type 5 (SS-PDB400-T05)
400A DB Type 5
SS-PDB400-T05
400A DB Type 6
SS-PDB400-T06
400A DB Type 7
SS-PDB400-T07

630A DB Type 1

SS-PDB630-T01

Image description

TEMPORARY CABLING

PRIMARY AND SECONDARY POWER CABLING.

Temporary sites can require extensive cable networks connecting generators, mains supplies, distribution boards and individual electrical loads.


Evolution Site maintains PowerLock cables in several sizes, together with 16A, 32A, 63A and 125A distribution cables. Splitters, jumpers, tails and adapters are also available to complete the required temporary connections.

CABLES AND CONNECTIONS FOR TEMPORARY DISTRIBUTION

Cable selection depends on the electrical demand, phase, connection type, cable distance and the equipment being supplied. Correct sizing and specification ensure that power is delivered safely and efficiently without excessive voltage drop or unnecessary heat build-up over longer runs.


Cables can be hired individually or supplied in the quantities and configurations required for a complete distribution system. This flexibility allows the temporary electrical network to be tailored precisely to the project’s layout, load profile and operational requirements.

PRIMARY CABLES

PowerLock Cables 120mm
SS-PPL120
PowerLock Cables 150mm
SS-PPL150
PowerLock Cables 240mm
SS-PPL240

SECONDARY CABLES

16A 1PH Cable
SS-P1P205
32A 1PH Cable
SS-P1P004
32A 3PH Cable
SS-P3P006
63A 3PH Cable
SS-P3P016
125A 3PH Cable
SS-P3P035

SPLITTER CABLES

16A Splitter Cable - 2x 16A 1PH
SS-PSP1PH-T09
32A 1PH Splitter Cable - 2x 16A 1PH 
SS-PSP1PH-T10 
32A 3PH Splitter Cable - 2x 32A 3PH 
SS-PSP3PH-T01
63A Splitter Cable - 2x 32A 3PH 
SS-PSP3PH-T02
63A Splitter Cable - 2x 63A 3PH 
SS-PSP3PH-T03
125A Splitter Cable - 2x 63A 3PH 
SS-PSP3PH-T04

JUMPER CABLES

32A - 63A 3PH Jumper Cable 
SS-PJC3PH-T01
16A to 2 x Shucko Adapter 
SS-PJC1PH-T02
13A - 16A 1PH Jumper Cable
SS-PJC1PH-T01
63A - 125A 3PH Jumper Cable 
SS-PJC3PH-T02
125A - 63A 3PH Jumper Cable 
SS-PJC3PH-T03

125A 3PH Male to PowerLock Female Jumper Cable ​

SS-PJC3PH-T04

PowerLock Male to 125A 3PH Female Jumper Cable ​

SS-PJC3PH-T05

13A - 4 Way Power Board 1 Meter
SS-PJC1PH-T03
16A - 4 Way Power Board 1 Meter
SS-PJC1PH-T05

TAIL CABLES

240mm PowerLock - 2.5m Male Tail
SS-PPL240-MTL
125A 3PH - 2.5m Male Tail
SS-P3P035-MTL
240mm PowerLock - 2.5m Female Tail
SS-PPL240-FTL
125A 3PH - 2.5m Female Tail
SS-P3P035-FTL
150mm PowerLock - 2.5m Male Tail 
SS-PPL150-MTL
63A 3PH - 2.5m Male Tail
SS-P3P016-MTL

150mm PowerLock - 2.5m Female Tail 

SS-PPL150-FTL

63A 3PH - 2.5m Female Tail
SS-P3P016-FTL
120mm PowerLock - 2.5m Male Tail
SS-PPL120-MTL
32A 3PH - 2.5m Male Tail
SS-P3P006-MTL
120mm PowerLock - 2.5m Female Tail
SS-PPL120-FTL
32A 3PH - 2.5m Female Tail
SS-P3P006-FTL
Image description

CABLE MANAGEMENT

CABLE RAMPS AND ROUTE PLANNING.

Temporary cables may need to cross pedestrian routes, working areas and vehicle-access points.


Evolution Site supplies cable ramps in several configurations and can incorporate cable routes and protection into the wider temporary power plan.

PROTECTING CABLES AND ACCESS ROUTES

Cable routes should be planned around the site layout, distribution-board positions and areas requiring power.


Where cables cross access routes, suitable protection can help reduce direct contact with pedestrians and vehicles while keeping the electrical network organised.


Where practical, cable routes can also be coordinated with back-of-house areas and temporary structures to reduce their effect on guest-facing environments.

CABLE RAMPS

1 Channel Cable Ramp - Standard
SS-PCR1CH-T01
2 Channel Cable Ramp - Standard
SS-PCR2CH-T01 
3 Channel Cable Ramp - Standard
SS-PCR3CH-T01 
5 Channel Cable Ramp - Standard  ​
SS-PCR5CH-T01 
5 Channel Cable Ramp - ADA Compliant ​
SS-PCR5CH-ADA 
Image description

SITE LIGHTING

TEMPORARY FLOOD AND WORKING LIGHTING.

Evolution Site supplies temporary lighting for operational compounds, access routes, parking areas, working areas and other site environments.


Our inventory includes LED floodlights in several outputs, halogen floodlights and LED tube lights. Lighting can be hired independently or incorporated into the wider temporary distribution system.

LIGHTING PLANNED WITH THE POWER NETWORK

Temporary lighting positions, electrical supply and cable routes can be planned together as part of the wider site layout. Coordinating these elements from the outset helps ensure that lighting is both effective and practical, with power available where it is needed and cable runs kept clear of key access routes and working areas.


Requirements often differ between build-up, live operations and de-rig. Lighting quantities and positions can therefore be reviewed as working areas, access routes and operational compounds evolve. Evolution’s experience includes secondary power distribution and site-lighting delivery for Emirates 7s, demonstrating the ability to adapt temporary lighting and power solutions to the changing demands of a major event.

FLOOD + WORKING LIGHTING

Flood Light - LED - 50 Watt
SS-LFL050-T01
Flood Light - LED - 500 Watt​
SS-LFL500-T07
Flood Light - LED - 100 Watt
SS-LFL100-T02
Flood Light - Halogen - 1000 Watt​
SS-LFL01K-T08
Flood Light - LED - 200 Watt
SS-LFL200-T03
Tube Light - LED - 22 Watt
SS-LSL022-T01
Flood Light - LED - 200 Watt Slim​
SS-LFL200-T04
Flood Light - LED - 300 Watt
SS-LFL300-T05
Image description

INSTALLATION + COMMISSIONING

INSTALLED, TESTED AND COMMISSIONED.

Evolution Site’s electrical teams can install temporary distribution boards, cabling and associated power infrastructure according to the project requirements.


Equipment can also be hired without installation where the client or appointed electrical contractor will manage the system.

PREPARED FOR OPERATION

Depending on the agreed scope, installation services can include generator and equipment positioning, primary and secondary cabling, distribution-board installation, connection of temporary loads, cable-route organisation and protection, load balancing, electrical testing, system commissioning, and phased installation as site areas become available.


The complete system can be checked before operational handover, with relevant documentation prepared according to the project requirements. This structured approach ensures that the temporary electrical infrastructure is correctly installed, tested and ready for reliable use throughout the event.

Image description

BACKUP + CONTINGENCY

CONTINGENCY FOR CRITICAL LOADS.

Not every electrical load requires the same level of backup.


Critical production, medical, security, broadcast and operational systems may require additional protection against interruption. Other non-critical loads may not justify the same level of redundancy.


The contingency strategy should reflect the consequence of losing each supply.

BACKUP WHERE IT IS REQUIRED

Critical loads can be identified during the planning stage so that suitable contingency arrangements are incorporated into the system from the outset. Depending on the project, these measures may include backup generators, synchronised generation, separate supplies for critical systems, alternative distribution routes, additional distribution equipment, planned response procedures and technical monitoring during operation.


This approach provides targeted protection for important systems without adding unnecessary equipment to every part of the site. By focusing contingency resources where they are most needed, the temporary power network remains efficient, resilient and correctly matched to operational priorities.

Image description

TECHNICAL SUPPORT

ELECTRICAL SUPPORT THROUGHOUT THE PROJECT.

Temporary power systems can change as additional equipment is introduced, operating schedules develop and different areas of the site become active.


Evolution Site can provide electrical personnel during installation and live operations to monitor the system, support planned changes and respond to technical issues.

FROM INSTALLATION TO DE-RIG

Depending on the project requirements, technical support can include generator and distribution monitoring, routine inspections, preventative maintenance, fuel monitoring and refuelling coordination, electrical fault response, approved changes to the distribution network, support for additional loads, isolation and disconnection, and equipment removal during de-rig.


The required number of technicians and their working hours can be planned around the size, complexity and operating schedule of the temporary power system. This ensures that appropriate technical cover is available throughout the project without unnecessary over-resourcing.


Image description

ELECTRICAL SAFETY

PLANNED FOR TEMPORARY ENVIROMENTS.

Temporary power systems operate across working sites, public environments and areas shared by several contractors and departments.


Electrical equipment, connections and cable routes must therefore be planned around both the technical requirements and the people, vehicles and other infrastructure using the site.

SAFETY THROUGHOUT THE SYSTEM

Depending on the project scope, temporary power delivery can include load assessments, project-specific risk assessments, method statements, planned cable routes, cable protection, electrical testing, equipment inspections, controlled system changes, documented operating procedures and ongoing technical monitoring.


Evolution’s electrical delivery is supported by ISO 9001, ISO 14001 and ISO 45001 certified management systems. These frameworks help ensure that temporary power systems are planned, installed and operated to consistent standards of quality, environmental responsibility and safety throughout the project.

Image description

EQUIPMENT RENTAL + COMPLETE SYSTEMS

HIRE INDIVIDUAL EQUIPMENT OR A COMPLETE POWER PACKAGE.

Clients can hire generators, distribution boards, PowerLock cables, secondary cabling, splitter cables, adapters, cable ramps and temporary site lighting as individual equipment categories.


For projects requiring wider support, Evolution Site can calculate, plan, install and maintain a complete temporary power system.

SELECT THE LEVEL OF SUPPORT YOU NEED

Available services can include individual equipment rental, electrical load calculations, temporary power planning, generation, primary and secondary distribution, cabling and connections, cable management, temporary site lighting, installation and commissioning, backup and contingency planning, fuel coordination, live technical support, and de-rig and equipment removal.


Evolution can work from a defined equipment list or review the site information and recommend the equipment and services required.


RELIABLE POWER FOR EVERY PROJECT

From a single electrical circuit to complete site-wide distribution, Evolution Site provides temporary power solutions designed around the needs of each project. We support everything from small activations requiring basic power connections to major events with multiple generators, distribution points and extensive cabling.


Our team can manage power planning, generation, distribution, cabling, connections and on-site technical support. With careful planning and reliable delivery, we help ensure temporary power systems remain safe, efficient and ready to support operations throughout the project.

Image description

BUILT TO SCALE

FROM ONE CIRCUIT TO SITE-WIDE DISTRIBUTION.

A temporary activation may require a simple electrical supply and a small number of distribution points. A festival, sporting event or public programme may require several generators, extensive cabling, multiple distribution stages and hundreds of individual loads.


Evolution Site supports both individual equipment requirements and complete temporary power systems for projects of different scales and durations.


Our experience includes full temporary power support for Liwa Village 2023, power and site infrastructure for the Platform Desert Cycle Event, and integrated HVAC and power delivery for the EuroLeague Semi-Finals. 

Image description

TEMPORARY POWER

TELL US WHAT NEEDS POWER.

Send us the site plan, equipment schedule, operating dates and available electrical information.


Our team can help calculate the load and recommend the generation, distribution, cabling and technical support required for the project.

EXPLORE OUR BROCHURE

LET'S TALK...


Temporary sites need practical spaces for the people, equipment and materials that keep them operating. Site offices, welfare facilities, toilets, showers and secure storage may sit behind the scenes, but their location, capacity and accessibility can have a significant impact on how efficiently the wider site functions.


At Evolution Site, we help plan and provide cabins, ablutions and storage around the specific requirements of each project. Workforce and guest numbers, operating hours, site layout, access, servicing requirements and available space can all be considered when determining the right facilities and where they should be positioned.


From site offices, changing rooms and staff welfare facilities to standard and VIP ablutions, showers and temporary storage, solutions can be configured and scaled to support the project throughout build-up, live operations and de-rig.


Planning cabins, ablutions or temporary storage for an event, venue or project across the UAE, Saudi Arabia or wider GCC?... speak with the Evolution Site team.

*

*

*

*

*

*

*

*

CONTACT DETAILS

LOOKING FOR WORK?

Please do not send CVs to our general enquiry email.


All job applications and freelance enquiries should be submitted through our careers page so they reach the right team.

POWER SOLUTION FAQs

What temporary power solutions does Evolution Site provide?

Evolution Site provides generators, transformers, fuel equipment, distribution boards from 32A to 630A, PowerLock cables, secondary cabling, splitter cables, adapters, cable ramps, batteries and temporary site lighting.

What types of projects can Evolution’s temporary power systems support?

Temporary power can support festivals, concerts, sporting events, exhibitions, conferences, government programmes, hospitality environments, temporary offices, workforce compounds and other temporary sites.

Do you provide temporary power for events in Dubai and the UAE?

Yes. Evolution Site provides temporary power equipment, electrical distribution, cabling, planning and technical support across Dubai, Abu Dhabi and the wider UAE.

Do you provide temporary power in Saudi Arabia?

Yes. Supported by our permanent facility in Riyadh, Evolution Site provides temporary power equipment and services for projects throughout Saudi Arabia.

Where does Evolution Site provide temporary power solutions?

Evolution Site supports temporary power projects throughout the UAE and Saudi Arabia, with the capability to work across the wider GCC and selected international destinations.

Can clients hire individual electrical equipment or appoint Evolution for a complete power package?

Both. Clients can hire individual generators, distribution boards, cables, cable ramps or lighting equipment, or appoint Evolution to plan, install and support a complete temporary power system.

Can you calculate how much power our project needs?

Yes. Our team can assess anticipated electrical loads, operating requirements, site layout, distribution distances and critical systems to help determine an appropriate temporary power strategy

What information is required to calculate temporary power?

We generally need an equipment and load schedule, operating periods, phase and connection requirements, equipment locations and information about any critical systems. The exact information required will depend on the project’s complexity.

Do you rent generators?

Yes. Evolution Site maintains selected temporary generators and can incorporate appropriate generation into wider temporary power solutions.

Do you only provide generators from your own inventory?

No. The generation strategy can incorporate additional equipment where the project requires a capacity or configuration beyond Evolution’s own generator inventory.

Do you rent electrical distribution boards?

Yes. Evolution Site supplies temporary distribution boards in several configurations, with ratings ranging from 32A to 630A.

Do you provide primary and secondary electrical distribution?

Yes. Evolution Site can provide primary and secondary distribution equipment, cabling and installation according to the temporary system requirements.

Do you rent PowerLock cables?

Yes. Our primary cable inventory includes 120mm, 150mm and 240mm PowerLock cables, together with compatible male and female tails.

What other temporary electrical cables do you supply?

Our inventory includes 16A, 32A, 63A and 125A cabling, together with splitter cables, jumper cables, tails, adapters and temporary power boards.

Can Evolution install and commission the temporary electrical system?

Yes. Depending on the scope, our electrical teams can support equipment positioning, cabling, distribution-board installation, connections, load balancing, electrical testing and commissioning.

Do you provide electrical technicians during live operations?

Yes. Technical personnel can support installation and live operations, with staffing and working hours determined by the scale, complexity and operating schedule of the project.

Can temporary power systems include backup and redundancy?

Yes. Critical loads can be supported through backup generation, synchronised equipment, separate supplies or alternative distribution arrangements where required.

Can you provide power for audiovisual and production equipment?

Yes. Temporary systems can support audiovisual equipment, event lighting, broadcast facilities and other production infrastructure, subject to the confirmed electrical requirements.

Can you provide power for temporary HVAC systems?

Yes. HVAC loads can be included within the wider power calculation and distribution strategy. The EuroLeague Semi-Finals demonstrate Evolution’s experience integrating temporary HVAC and power delivery.

Can you provide power for temporary kitchens and catering areas?

Yes. Catering equipment, refrigeration and kitchen loads can be incorporated into the load assessment and temporary distribution plan.

Can you provide power for cabins and operational compounds?

Yes. Temporary offices, production compounds, welfare facilities, security cabins and other site infrastructure can be included within the temporary power system.

Do you provide temporary site lighting?

Yes. Evolution Site supplies LED and halogen floodlights and LED tube lights for compounds, routes, work areas and other temporary site environments.

Do you provide cable ramps?

Yes. Our inventory includes standard one, two, three and five-channel cable ramps, together with an ADA-compliant five-channel option.

Can you plan cable routes around pedestrians and vehicles?

Yes. Cable routes and suitable protection can be planned around pedestrian areas, working routes, vehicle movements and other site infrastructure.

Can you provide temporary power in remote locations?

Yes. Temporary generation and distribution can be established in locations where permanent electrical infrastructure is unavailable or insufficient, subject to the project requirements and site conditions.

Can temporary power support short-term and long-term projects?

Yes. Temporary systems can support single-day events, multi-day programmes and projects operating for several weeks or months, with servicing and technical support planned accordingly.

Can Evolution manage generator fuel?

Yes. Depending on the scope, Evolution can plan fuel storage, monitor consumption and coordinate scheduled refuelling throughout the operational period.

How are generator and distribution-board locations determined?

Locations are influenced by the electrical loads, cable distances, site access, equipment ventilation, fuel servicing, noise considerations, operational requirements, safety and other temporary infrastructure.